 PERFORMANCE ORDER

1. Remove the air filter.
2. Merge cooling liquid.
3. Disconnect conducting sockets around the inlet pipeline or on it.
4. Unhook a guide for high-voltage wires.
5. Disconnect vacuum tubes from the inlet pipeline.
6. Reduce fuel pressure by means of the special valve on the fuel distributor.
7. Turn off forcing (17/3) and returnable (17/2) fuel-supply lines.
8. Disconnect a vacuum tube from the vacuum amplifier of brakes.
9. Remove a guide (27).
10. Disconnect a cable (30) from a control lever a butterfly valve (9).
11. Remove a cable (30) from the lever (10). His Vypressuyte together with a plastic clamp (28).
12. Disconnect a cable (98).
13. Disconnect a branch pipe of the cooling system (33) in a forward part of the inlet pipeline.
14. Disconnect a cooling system branch pipe in a back part of the inlet pipeline.
15. Turn off bolts (14), (15) and (16).
16. Remove the inlet pipeline (19).
17. Replace laying (18).

Installation

Installation is made as it should be, the return to removal. The order of tightening of bolts of fastening of the inlet pipeline is shown on an illustration.

 

Engines of the M119.98 series

Removal

Details of installation of the inlet pipeline (M119.98 engines)


 PERFORMANCE ORDER

1. Remove the fuel distributive highway together with injectors.
2. Remove the measuring instrument of an air stream.
3. Merge cooling liquid.
4. Disconnect the conducting socket from the case of a butterfly valve (M16/1x1).
5. Disconnect all connections of an electrical wiring on the inlet pipeline.
6. Disconnect a vacuum tube from the test valve.
7. Disconnect a branch pipe of the cooling system (33/1) in a back part of the inlet pipeline.
8. Disconnect a branch pipe of the cooling system (33) in a forward part of the inlet pipeline.
9. Turn off fastening bolts (14), (15) and (16) inlet pipelines.
10. Remove the inlet pipeline (19).
11. Replace laying (18).

Installation

Installation is made as it should be, the return to removal. The order of tightening of bolts of fastening of a head of the block of cylinders is shown on an illustration.