90fcb7d0

9.4.3. Dismantling and assembly of a plate of gear shifting

Details of installation of a plate of gear shifting

Gear shifting plate

A — the Valve of adjustment of working pressure. Valve of adjustment of pressure of lubricant. The valve of adjustment of overlapping at inclusion of 2-3 transfers
In — the Block of inclusion of 1-2/4-5 transfers

Valve of adjustment of pressure of gear shifting
With — the Block of inclusion of 3-4 transfers
D — the Block of inclusion of 2-3 transfers. Coupling of blocking of the adjusting valve. Adjusting B2 valve

Dismantling

Dismantling of a plate of gear shifting

71 — Bolts
72 — the Cover of valvate assembly
73 — the Sealing plate
74 — Valvate assembly
82 — the Clamp

 


Dismantling of a plate of gear shifting

59 — the Directing finger
75 — Plastic ball valves
76 — Steel ball valves
143 — the Central clamp

 


Dismantling of a plate of gear shifting

72 — Valvate assembly
72.1 — Transfer choice valve
72.2 — The valve of adjustment of blocking of 2-3 transfers with the plug and the piston
72.3 — Valve of adjustment of pressure of lubricant
72.4 — Valve of adjustment of working pressure

72.5 — Valve of fixing of inclusion of 3-4 transfers
72.6 — The operating valve of inclusion of 3-4 transfers
72.7 — The valve of switching of pressure at inclusion of 3-4 transfers
72.8 — The valve of adjustment of blocking of 3-4 transfers with the plug and the piston


Dismantling of a plate of gear shifting

74 — Valvate assembly
74.14 — The operating valve of inclusion of 1-2/4-5 transfers
74.15 — Valve of fixing of inclusion of 1-2/4-5 transfers
74.18 — The valve of adjustment of blocking of 1-2/4-5 transfers with the plug and the piston
74.19 — Valve of adjustment of pressure of gear shifting
74.20 — Valve of adjustment of pressure of the adjusting valve

74.21 — The valve of adjustment of pressure of the switching valve
74.22 — Blocking adjustment valve hydrotransformer
74.24 — The valve of switching of pressure at inclusion of 3-4 transfers
74.25 — The operating valve of inclusion of 2-3 transfers
74.26 — Valve of fixing of inclusion of 2-3 transfers
74.27 — Valve of switching B2


 PERFORMANCE ORDER

1. Turn off clamps (82).
2. Turn off bolts (71).
3. Uncover valvate assembly (72) valvate assembly (74).
4. Remove a sealing plate (73). All 12 balls are located in the case of valves, four 75 of which - plastic, other eight (76) - steel.
5. Turn off covers of the case of valves. Plugs and pistons of adjusting valves (72.2), (72.8) and (74.18) should not be mixed.
6. The valve of switching B2 can be removed and installed when the case of valves is uncovered.

Assembly

Dismantling of a plate of gear shifting

59 — the Directing finger
75 — Plastic ball valves
76 — Steel ball valves
143 — the Central clamp

 


Assembly is carried out as it should be, the return to dismantling. Implant the directing finger (59) into the case of valves (shooter).