4.7.7. Removal and installation of a head of the block of cylinders
Removal 
 Preparation for removal of a head of the block of cylinders 
| 
 | 
1 — the Inlet pipe   3, 7 — Decorative panels   4 — the Exhaust pipe   4a — the Final collector   5, 62 — Arms   6 — the Tube of recirculation of the fulfilled gases   8 — the Inlet pipeline  
 | 
 9 — the Wire of a candle of a nakaliv a niya   10 — the Air filter   11 — the Air inlet tube   12 — the Fuel filter   13 — the Valve of recirculation of the fulfilled gases   93 — the Cranked branch pipe   120 — the Battery   155 — the Basic rack   X26/2 — the conducting Socket   | 
| 
 | 
| 
 1. Remove the camshaft.   2. Remove injectors.   3. Take off a generator drive belt.   4. Disconnect a negative wire from the battery (120).   5. Disconnect an air inlet pipe (11) and a cover of the air filter (10) together with the filtering element.   6. Remove decorative panels (3) and (7).   7. Disconnect an inlet pipe (1) from a turbocompressor.   8. Turn off a basic rack (155) of a returnable tube.   9. Turn off the forcing oil pipeline from the block of cylinders.   10. Remove the fuel filter (12).   11. Turn off an arm (62) guides of a pipe of the index of level of oil.   12. Pick up the phone (6) between the valve of recirculation of the fulfilled gases and the inlet pipeline or a tube of supply of compressed air.   13. Disconnect the valve of recirculation of the fulfilled gases (13).   14. Turn off an exhaust pipe (4) from a final collector.   15. Turn off wires (9) from incandescence candles.   16. Disconnect the socket (X26/2).   17. Remove the inlet pipeline (8).   | 
 
 
 | 
 Details of installation of a head of the block of cylinders (really cylinders 6) 
| 
 | 
| 
 15 — the Sliding lever   16, 17, 18, 19 — Bolts   20 — the Head of the block of cylinders   21 — Laying   221, 222 — Fingers of the sliding lever   | 
    | 
| 
 | 
1. Take fingers (221), (222) sliding levers from a head of the block of cylinders.   2. Remove the sliding lever (15).   3. Turn off a bolt (16) of fastening of a cover of a chain of the GRM drive to a head of the block of cylinders.  | 
 
| 4. Turn off bolts of fastening of a head of the block of cylinders (17), (18) and (19) as it should be, the return shown on an illustration.  | 
 | 
 
 5. Remove a head of the block of cylinders (20) together with laying (21).   6. Wipe openings under bolts of a head of the block of cylinders.  | 
 
 
 | 
Installation 
| 
 | 
  Installation is carried out as it should be, the return to removal. The order of tightening of bolts of fastening of a head of cylinders is shown on an illustration.   |